Channel Tunnel

Channel Tunnel
Map of the Channel Tunnel
Overview
Location English Channel (Strait of Dover)
Coordinates Folkestone:
Coquelles:
Status Active
Start Folkestone, Kent, United Kingdom
End Coquelles, Pas-de-Calais, France
Operation
Opened 6 May 1994 (tunnel)
14 November 1994 (passenger service)
Owner Eurotunnel
Operator Eurotunnel
Eurostar
DB Schenker Rail (UK)
Character Through-rail passenger and freight. Vehicle shuttle.
Technical
Line length 50.45 km (31.35 mi)
No. of tracks 2 single track tunnels
1 service tunnel
Gauge 1,435 mm (4 ft 8 12 in) (standard gauge)
Electrified 25 kV AC OHLE

The Channel Tunnel (French: Le tunnel sous la Manche; also referred to as the Chunnel)[1][2] is a 50.5-kilometre (31.4 mi) undersea rail tunnel linking Folkestone, Kent, in the United Kingdom with Coquelles, Pas-de-Calais, near Calais in northern France beneath the English Channel at the Strait of Dover. At its lowest point, it is 75 metres (250 ft) deep.[3][4][5] At 37.9 kilometres (23.5 mi), the Channel Tunnel possesses the longest undersea portion of any tunnel in the world, although the Seikan Tunnel in Japan is both longer overall at 53.85 kilometres (33.46 mi), and deeper at 240 metres (790 ft) below sea level.

The tunnel carries high-speed Eurostar passenger trains, Eurotunnel Shuttle roll-on/roll-off vehicle transport—the largest in the world—and international rail freight trains.[6] The tunnel connects end-to-end with the LGV Nord and High Speed 1 high-speed railway lines. In 1996 the American Society of Civil Engineers identified the tunnel as one of the Seven Wonders of the Modern World.[7]

Ideas for a cross-Channel fixed link appeared as early as 1802,[8][9] but British political and press pressure over compromised national security stalled attempts to construct a tunnel.[10] However, the eventual successful project, organised by Eurotunnel, began construction in 1988 and opened in 1994. The project came in 80% over its predicted budget.[11] Since its construction, the tunnel has faced several problems. Fires have disrupted operation of the tunnel. Illegal immigrants and asylum seekers have attempted to use the tunnel to enter the UK,[12] causing a minor diplomatic disagreement over the siting of the Sangatte refugee camp, which was eventually closed in 2002.[13]

Contents

Origins

Proposals and attempts

Key dates
1802 Albert Mathieu put forward a cross-Channel tunnel proposal.
1875 The Channel Tunnel Company Ltd[14] began preliminary trials
1882 The Abbot's Cliff heading had reached 897 yards (820 m) and that at Shakespeare Cliff was 2,040 yards (1,870 m) in length
January 1975 A UK–France government backed scheme that started in 1974 was cancelled
February 1986 The Treaty of Canterbury was signed allowing the project to proceed
June 1988 First tunnelling commenced in France
December 1988 UK TBM commenced operation
December 1990 The service tunnel broke through under the Channel
May 1994 The tunnel was formally opened by HM The Queen and President Mitterrand
Mid 1994 Freight and passenger trains commenced operation
November 1996 A fire in a lorry shuttle severely damaged the tunnel
November 2007 High Speed 1, linking London to the tunnel, opened
September 2008 Another fire in a lorry shuttle severely damaged the tunnel
December 2009 Eurostar trains stranded in the tunnel due to melting snow affecting the trains' electrical hardware

In 1802, French mining engineer Albert Mathieu put forward a proposal to tunnel under the English Channel, with illumination from oil lamps, horse-drawn coaches, and an artificial island mid-Channel for changing horses.[8]

In the 1830s, Frenchman Aimé Thomé de Gamond performed the first geological and hydrographical surveys on the Channel, between Calais and Dover. Thomé de Gamond explored several schemes and, in 1856, he presented a proposal to Napoleon III for a mined railway tunnel from Cap Gris-Nez to Eastwater Point with a port/airshaft on the Varne sandbank[15] at a cost of 170 million francs, or less than £7 million.[16]

In 1865, a deputation led by George Ward Hunt proposed the idea of a tunnel to the Chancellor of the Exchequer of the day, William Ewart Gladstone.[17]

After 1867, William Low and Sir John Clarke Hawkshaw promoted ideas, but none were implemented. An official Anglo-French protocol was established in 1876 for a cross-Channel railway tunnel. In 1881, British railway entrepreneur Sir Edward Watkin and French Suez Canal contractor Alexandre Lavalley were in the Anglo-French Submarine Railway Company that conducted exploratory work on both sides of the Channel. On the English side a 2.13-metre (7 ft) diameter Beaumont-English boring machine dug a 1,893-metre (6,211 ft) pilot tunnel from Shakespeare Cliff. On the French side, a similar machine dug 1,669 m (5,476 ft) from Sangatte. The project was abandoned in May 1882, owing to British political and press campaigns advocating that a tunnel would compromise Britain's national defences.[10] These early works were encountered more than a century later during the TML project.

In 1919, during the Paris Peace Conference, British Prime Minister David Lloyd George repeatedly brought up the idea of a Channel tunnel as a way of reassuring France about British willingness to defend against another German attack. The French did not take the idea seriously and nothing came of Lloyd George's proposal.[18]

In 1929 there was another proposal for the building a channel tunnel, but nothing came of this discussion and the idea was shelved. Proponents estimated construction to be about US$150 million. The engineers addressed the concerns of both nations' military leaders by designing two sumps—one near the coast of each country—that could be flooded at will to block the tunnel. This design feature did not override the concerns of both nations' military leaders, and other concerns for hordes of undesirable tourists who would disrupt English habits of living.[19]

In 1955, defence arguments were accepted to be irrelevant because of the dominance of air power; thus, both the British and French governments supported technical and geological surveys. A detailed geological survey was carried out in 1964–65.[20] Construction work commenced on both sides of the Channel in 1974, a government-funded project using twin tunnels on either side of a service tunnel, with capability for car shuttle wagons. In January 1975, to the dismay of the French partners, the British government cancelled the project. The government had changed to the Labour Party and there was uncertainty about EEC membership, cost estimates had ballooned to 200% and the national economy was troubled. By this time the British Priestly tunnel boring machine was ready and the Ministry of Transport was able to do a 300 m (980 ft) experimental drive.[10] This short tunnel would however be reused as the starting and access point for tunnelling operations from the British side.

In 1979, the "Mouse-hole Project" was suggested when the Conservatives came to power in Britain. The concept was a single-track rail tunnel with a service tunnel, but without shuttle terminals. The British government took no interest in funding the project, but Prime Minister Margaret Thatcher said she had no objection to a privately funded project. In 1981 British and French leaders Margaret Thatcher and François Mitterrand agreed to set up a working group to look into a privately funded project, and in April 1985 promoters were formally invited to submit scheme proposals. Four submissions were shortlisted:

The cross-Channel ferry industry protested under the name "Flexilink". In 1975 there was no campaign protesting against a fixed link, with one of the largest ferry operators (Sealink) being state-owned. Flexilink continued rousing opposition throughout 1986 and 1987.[10] Public opinion strongly favoured a drive-through tunnel, but ventilation issues, concerns about accident management, and fear of driver mesmerisation led to the only shortlisted rail submission, CTG/F-M, being awarded the project.[10]

Arrangement

The British Channel Tunnel Group consisted of two banks and five construction companies, while their French counterparts, France–Manche, consisted of three banks and five construction companies. The role of the banks was to advise on financing and secure loan commitments. On 2 July 1985, the groups formed Channel Tunnel Group/France–Manche (CTG/F–M). Their submission to the British and French governments was drawn from the 1975 project, including 11 volumes and a substantial environmental impact statement.[10]

The design and construction was done by the ten construction companies in the CTG/F-M group. The French terminal and boring from Sangatte was undertaken by the five French construction companies in the joint venture group GIE Transmanche Construction. The English Terminal and boring from Shakespeare Cliff was undertaken by the five British construction companies in the Trankslink Joint Venture. The two partnerships were linked by TransManche Link (TML), a bi-national project organisation.[10] The Maître d'Oeuvre was a supervisory engineering body employed by Eurotunnel under the terms of the concession that monitored project activity and reported back to the governments and banks.[21]

In France, with its long tradition of infrastructure investment, the project garnered widespread approval and in April the French National Assembly gave unanimous support and, in June 1987, after a public inquiry, the Senate gave unanimous support. In Britain, select committees examined the proposal, making history by holding hearings outside of Westminster, in Kent. In February 1987, the third reading of the Channel Tunnel Bill took place in the House of Commons, and was carried by 94 votes to 22. The Channel Tunnel Act gained Royal assent and passed into English law in July of that year.[10] Parliamentary support for the project came partly from provincial members of Parliament on the basis of promises of regional Eurostar through train services that have never materialised; the promises were repeated in 1996 when the contract for construction of the Channel Tunnel Rail Link was awarded.[22]

The Channel Tunnel is a build-own-operate-transfer (BOOT) project with a concession.[23] TML would design and build the tunnel, but financing was through a separate legal entity: Eurotunnel. Eurotunnel absorbed CTG/F-M and signed a construction contract with TML; however, the British and French governments controlled final engineering and safety decisions, which are now in the hands of the Channel Tunnel Safety Authority. The British and French governments gave Eurotunnel a 55- (later 65-) year operating concession to repay loans and pay dividends. A Railway Usage Agreement was signed between Eurotunnel, British Rail and the Société Nationale des Chemins de fer Français guaranteeing future revenue in exchange for the railways obtaining half of the tunnel's capacity.

Private funding for such a complex infrastructure project was of unprecedented scale. An initial equity of £45 million was raised by CTG/F-M, increased by £206 million private institutional placement, £770 million was raised in a public share offer that included press and television advertisements, a syndicated bank loan and letter of credit arranged £5 billion.[10] Privately financed, the total investment costs at 1985 prices were £2600 million. At the 1994 completion actual costs were, in 1985 prices, £4650 million: an 80% cost overrun.[11] The cost overrun was partly due to enhanced safety, security, and environmental demands.[23] Financing costs were 140% higher than forecast.[24]

Construction

Working from both the English side and the French side of the Channel, eleven tunnel boring machines cut through chalk marl to construct two rail tunnels and a service tunnel. The vehicle shuttle terminals are at Cheriton (part of Folkestone) and Coquelles, and are connected to the English and French motorways (M20 and A16 respectively).

Tunnelling commenced in 1988, and the tunnel began operating in 1994.[25] In 1985 prices, the total construction cost was £4.650 billion (equivalent to £11 billion today), an 80% cost overrun. At the peak of construction 15,000 people were employed with daily expenditure over £3 million.[26] Ten workers, eight of them British, were killed during construction between 1987 and 1993, most in the first few months of boring.[27][28][29]

Completion

A small, two-inch (50-mm) diameter pilot hole allowed the service tunnel to break through without ceremony on 30 October 1990.[30] On 1 December 1990, Englishman Graham Fagg and Frenchman Phillippe Cozette broke through the service tunnel with the media watching.[31] Eurotunnel completed the tunnel on time,[23] and the tunnel was officially opened one year later than originally planned by British Queen Elizabeth II and French President François Mitterrand in a ceremony held in Calais on 6 May 1994. The Queen travelled through the tunnel to Calais on a Eurostar train, which stopped nose to nose with the train that carried President Mitterrand from Paris.[32] Following the ceremony President Mitterrand and the Queen travelled on Le Shuttle to a similar ceremony in Folkestone.[32] A full public service did not start for several months.

The Channel Tunnel Rail Link (CTRL), now called High Speed 1, runs 69 miles (111 km) from St Pancras railway station in London to the Channel Tunnel portal at Folkestone in Kent. It cost £5.8 billion. On 16 September 2003 UK Prime Minister Tony Blair opened the first section of High Speed 1, from Folkestone to north Kent. On 6 November 2007 the Queen officially opened High Speed 1 and St Pancras International station,[33] replacing the original slower link to Waterloo International railway station. On High Speed 1 trains travelling at speeds up to 300 km/h (186 mph), the journey from London to Paris takes 2 hours 15 minutes and London to Brussels takes 1 hour 51 minutes.[34]

In 1996, the American Society of Civil Engineers, with Popular Mechanics, selected the tunnel as one of the Seven Wonders of the Modern World.[7]

Engineering

Surveying undertaken in the twenty years before tunnel construction confirmed earlier speculations that a tunnel route could be bored through a chalk marl stratum. The chalk marl was conducive to tunnelling, with impermeability, ease of excavation and strength. While on the English side the chalk marl ran along the entire length of the tunnel, on the French side a length of 5 kilometres (3 mi) had variable and difficult geology. The Channel Tunnel consists of three bores: two 7.6-metre (25 ft) diameter rail tunnels, 30 metres (98 ft) apart, 50 kilometres (31 mi) in length with a 4.8-metre (16 ft) diameter service tunnel in between. There are also cross-passages and piston relief ducts. The service tunnel was used as a pilot tunnel, boring ahead of the main tunnels to determine the conditions. English access was provided at Shakespeare Cliff, while French access came from a shaft at Sangatte. The French side used five tunnel boring machines (TBMs); the English side used six. The service tunnel uses Service Tunnel Transport System (STTS) and Light Service Tunnel Vehicles (LADOGS). Fire safety was a critical design issue.

Between the portals at Beussingue and Castle Hill the tunnel is 50.5 kilometres (31 mi) long, with 3.3 kilometres (2 mi) under land on the French side, 9.3 kilometres (6 mi) under land on the UK side and 37.9 kilometres (24 mi) under sea.[4] This makes the Channel Tunnel the second longest rail tunnel in the world, behind the Seikan Tunnel in Japan, but with the longest under-sea section.[35] The average depth is 45 metres (148 ft) below the seabed.[36] On the UK side, of the expected 5 million cubic metres (6.5×10^6 cu yd) of spoil approximately 1 million cubic metres (1.3×10^6 cu yd) was used for fill at the terminal site, and the remainder was deposited at Lower Shakespeare Cliff behind a seawall, reclaiming 74 acres (30 ha)[26] of land.[37] This land was then made into the Samphire Hoe Country Park. Environmental impact assessment did not identify any major risks for the project, and further studies into safety, noise, and air pollution were overall positive. However, environmental objections were raised over a high-speed link to London.[38]

Geology

Successful tunnelling under the channel required a sound understanding of the topography and geology and the selection of the best rock strata through which to tunnel. The geology generally consists of northeasterly dipping Cretaceous strata, part of the northern limb of the Wealden-Boulonnais dome. Characteristics include:

On the English side of the channel, the strata dip less than 5°, however, on the French side, this increases to 20°. Jointing and faulting is present on both the English and French sides. On the English side, only minor faults of displacement less than 2 metres (7 ft) exist. On the French side, displacements of up to 15 metres (49 ft) are present owing to the Quenocs anticlinal fold. The faults are of limited width, filled with calcite, pyrite and remoulded clay. The increased dip and faulting restricted the selection of route on the French side. To avoid confusion, microfossil assemblages were used to classify the chalk marl. On the French side, particularly near the coast, the chalk was harder, and more brittle, and more fractured than on the English side. This led to the adoption of different tunnelling techniques on the French and English sides.[40]

The Quaternary undersea valley Fosse Dangaered, and Castle Hill landslip, located at the English portal, caused concerns. Identified by the 1964–65 geophysical survey, the Fosse Dangaered is an infilled valley system extending 80 metres (262 ft) below the seabed, 500 metres (1,640 ft) south of the tunnel route, located mid-channel. A 1986 survey showed that a tributary crossed the path of the tunnel, and so the tunnel route was made as far north and deep as possible. The English terminal had to be located in the Castle Hill landslip, which consists of displaced and tipping blocks of lower chalk, glauconitic marl and gault debris. Thus the area was stabilised by buttressing and inserting drainage adits.[40] The service tunnels were pilot tunnels preceding the main tunnels, so that the geology, areas of crushed rock, and zones of high water inflow could be predicted. Exploratory probing took place in the service tunnels, in the form of extensive forward probing, vertical downward probes and sideways probing.[40]

Surveying

Marine soundings and samplings by Thomé de Gamond were carried out during 1833–1867, establishing the seabed depth at a maximum of 55 metres (180 ft) and the continuity of geological strata (layers). Surveying continued over many years, with 166 marine and 70 land-deep boreholes being drilled and over 4,000-line-kilometres of marine geophysical survey completed.[41] Surveys were undertaken in 1958–1959, 1964–1965, 1972–1974 and 1986–1988.

The surveying in 1958–1959 catered for immersed tube and bridge designs as well as a bored tunnel, and thus a wide area was investigated. At this time marine geophysics surveying for engineering projects was in its infancy, with poor positioning and resolution from seismic profiling. The 1964–1965 surveys concentrated on a northerly route that left the English coast at Dover harbour; using 70 boreholes, an area of deeply weathered rock with high permeability was located just south of Dover harbour.[41]

Given the previous survey results and access constraints, a more southerly route was investigated in the 1972–1973 survey and the route was confirmed to be feasible. Information for the tunnelling project also came from work before the 1975 cancellation. On the French side at Sangatte a deep shaft with adits was made. On the English side at Shakespeare Cliff, the government allowed 250 metres (820 ft) of 4.5-metre (15 ft) diameter tunnel to be driven. The actual tunnel alignment, method of excavation and support were essentially the same as the 1975 attempt. In the 1986–1997 survey, previous findings were reinforced and the nature of the gault clay and the tunnelling medium (chalk marl that made up 85% of the route) were investigated. Geophysical techniques from the oil industry were employed.[41]

Tunnelling

Tunnelling between England and France was a major engineering challenge, with the only precedent being the undersea Seikan Tunnel in Japan. A serious risk with underwater tunnels is major water inflow due to the water pressure from the sea above under weak ground conditions. The Channel Tunnel also had the challenge of time—being privately funded, early financial return was paramount.

The objective was to construct: two 7.6-metre (25 ft) diameter rail tunnels, 30 metres (98 ft) apart, 50 kilometres (31 mi) in length; a 4.8-metre (16 ft) diameter service tunnel between the two main tunnels; pairs of 3.3-metre (11 ft) diameter cross-passages linking the rail tunnels to the service tunnel at 375-metre (1,230 ft) spacing; piston relief ducts 2-metre (7 ft) diameter connecting the rail tunnels at 250-metre (820 ft) spacing; two undersea crossover caverns to connect the rail tunnels.[42] The service tunnel always preceded the main tunnels by at least 1 kilometre (0.6 mi) to ascertain the ground conditions. There was plenty of experience with tunnelling through chalk in the mining industry. The undersea crossover caverns were a complex engineering problem. The French cavern was based on the Mount Baker Ridge freeway tunnel in the US. The UK cavern was dug from the service tunnel ahead of the main tunnels to avoid delay.

Precast segmental linings in the main TBM drives were used, but different solutions were used on the English and French sides. On the French side, neoprene and grout sealed bolted linings made of cast iron or high-strength reinforced concrete were used. On the English side, the main requirement was for speed and bolting of cast-iron lining segments was only carried out in areas of poor geology. In the UK rail tunnels, eight lining segments plus a key segment were used; on the French side, five segments plus a key segment.[43] On the French side, a 55-metre (180 ft) diameter 75-metre (246 ft) deep grout-curtained shaft at Sangatte was used for access. On the English side, a marshalling area was 140 metres (459 ft) below the top of Shakespeare Cliff, and the New Austrian Tunnelling method (NATM) was first applied in the chalk marl here. On the English side, the land tunnels were driven from Shakespeare Cliff, the same place as the marine tunnels, not from Folkestone. The platform at the base of the cliff was not large enough for all of the drives and, despite environmental objections, tunnel spoil was placed behind a reinforced concrete seawall, on condition of placing the chalk in an enclosed lagoon to avoid wide dispersal of chalk fines. Owing to limited space, the precast lining factory was on the Isle of Grain in the Thames estuary.[42]

On the French side, owing to the greater permeability to water, earth pressure balance TBMs with open and closed modes were used. The TBMs were of a closed nature during the initial 5 kilometres (3 mi), but then operated as open, boring through the chalk marl stratum.[42] This minimised the impact to the ground and allowed high water pressures to be withstood, and it also alleviated the need to grout ahead of the tunnel. The French effort required five TBMs: two main marine machines, one main land machine (the short land drives of 3 km allowed one TBM to complete the first drive then reverse direction and complete the other), and two service tunnel machines. On the English side, the simpler geology allowed faster open-faced TBMs.[44] Six machines were used, all commenced digging from Shakespeare Cliff, three marine-bound and three for the land tunnels.[42] Towards the completion of the undersea drives, the UK TBMs were driven steeply downwards and buried clear of the tunnel. The French TBMs then completed the tunnel and were dismantled.[45] A 900 mm gauge railway was used on the English side during construction.[46]

In contrast to the English machines, which were simply given alphanumeric names, the French tunnelling machines were all named after women: Brigitte, Europa, Catherine, Virginie, Pascaline, Séverine.[47]

Railway design

Communications

There are three communication systems in the tunnel: concession radio (CR) for mobile vehicles and personnel within Eurotunnel's Concession (terminals, tunnels, coastal shafts); track-to-train radio (TTR) for secure speech and data between trains and the railway control centre; Shuttle internal radio (SIR) for communication between shuttle crew and to passengers over car radios.[48] This service was discontinued within one year of opening because of drivers difficulty setting their radios to the correct frequency (88.8 MHz).

Power supply

All tunnel services run on electricity, shared equally from English and French sources. Power is delivered to the locomotives via an overhead line (catenary)[49] at 25 kV 50 Hz.[50]

A large proportion of the railway south of London uses a 750 V DC third rail to deliver electrical power; however since the opening of High Speed 1 there is no need to use the third rail system for any part of the Eurostar journey. High Speed 1, the tunnel itself and the route to Paris has power provided via overhead catenary at 25 kV 50 Hz. The railways on "classic" lines in Belgium are also electrified by overhead catenaries, but at 3000 V DC.[50]

Signalling

A cab signalling system is used that gives information directly to train drivers on a display. There is Automatic Train Protection (ATP) that stops the train if the speed differs from that indicated on the in-cab display. TVM430, as used on LGV Nord, is used in the tunnel.[51] The maximum allowed speed is 160 km/h.[52]

Track system

The American Sonneville International Corporation track system was chosen, consisting of UIC60 rails on 900A grade resting on microcellular EVA pads, bolted into concrete.[53] The larger European GB+ loading gauge was used rather than one of the smaller UK alternatives; this gauge is maintained on High Speed 1 as far as Barking in east London.[54] Ballasted track was ruled out owing to maintenance constraints and a need for geometric stability.

Rolling stock

Eurotunnel Shuttle

Initially 38 Le Shuttle locomotives were commissioned, working in pairs with one at each end of a shuttle train. The shuttles have two separate halves: single and double deck. Each half has two loading/unloading wagons and twelve carrier wagons. Eurotunnel's original order was for nine tourist shuttles.

HGV shuttles also have two halves, with each half containing one loading wagon, one unloading wagon and 14 carrier wagons. There is a club car behind the leading locomotive. Eurotunnel originally ordered six HGV shuttles rakes.

Freight locomotives

Forty-six Class 92 locomotives for hauling freight trains and overnight passenger trains (the Nightstar project, which was abandoned) were commissioned, which can run on both overhead AC and third-rail DC power.

International passenger

Thirty-one Eurostar trains—based on the French TGV—built to UK loading gauge, and with many modifications for safety within the tunnel, were commissioned, with split ownership between British Rail, French National Railway Company and National Railway Company of Belgium. British Rail ordered seven more for services north of London.[55]

At the end of 2009, extensive fire-proofing requirements were dropped and Deutsche Bahn received permission to run German Intercity-Express (ICE) trains through the Channel Tunnel in the future. On 19 October 2010 Deutsche Bahn ran the first ICE train through the Channel Tunnel arriving in St. Pancras after evacuation tests in the tunnel were a success.[56][57][58]

Service locomotives

Diesel locomotives for rescue and shunting work are Eurotunnel Class 0001 and Eurotunnel Class 0031.

Operation

Usage and services

Services offered by the tunnel are:

Both the freight and passenger traffic forecasts that led to the construction of the tunnel were largely and universally overestimated. Particularly, Eurotunnel's commissioned forecasts were over-predictions.[59] Although the captured share of Channel crossings (competing with air and sea) was forecast correctly, high competition and reduced tariffs has led to low revenue. Overall cross-Channel traffic was overestimated.[60]

However with the EU's liberalisation of international rail services, the tunnel and High Speed 1 have been open to competition since 2010. There have been a number of operators interested in running services including Deutsche Bahn, through the tunnel and along High Speed 1 to London.

Passenger traffic volumes

Total cross-tunnel passenger traffic volumes peaked at 18.4 million in 1998, then dropped to 14.9 million in 2003, from then rising again to 17.0 million in 2010.

At the time of the decision about building the tunnel, 15.9 million passengers were predicted for Eurostar trains in the opening year. In 1995, the first full year, actual numbers were a little over 2.9 million, growing to 7.1 million in 2000, then dropping again to 6.3 million in 2003. However, Eurostar was also limited by the lack of a high-speed connection on the British side. After the completion of High Speed 1 (formerly CTRL) to London in two stages in 2003 and 2007, traffic increased. In 2008, Eurostar carried 9,113,371 passengers in cross-Channel-Tunnel traffic, a 10% increase over the previous year, despite traffic limitations due to the 2008 Channel Tunnel fire.[61] Eurostar passenger numbers continued to increase, reaching 9,528,558 in 2010.[62]

 Year  Passengers transported...
by Eurostar[A][63][64]
(actual ticket sales)
by Eurotunnel Passenger Shuttles[60][63]
(estimated, millions)
Total
(estimated, millions)
1994 ~100,000[60] 0.2 0.3
1995 2,920,309 4.4 7.3
1996 4,995,010 7.9 12.9
1997 6,004,268 8.6 14.6
1998 6,307,849 12.1 18.4
1999 6,593,247 11.0 17.6
2000 7,130,417 9.9 17.0
2001 6,947,135 9.4 16.3
2002 6,602,817 8.6 15.2
2003 6,314,795 8.6 14.9
2004 7,276,675 7.8 15.1
2005 7,454,497 8.2 15.7
2006 7,858,337 7.8 15.7
2007 8,260,980 7.9 16.2
2008 9,113,371 7.0 16.1
2009 9,220,233 6.9 16.1
2010[65] 9,528,558 7.5 17.0

A only passengers taking Eurostar to cross the Channel

Freight traffic volumes

Cross-tunnel freight traffic volumes have been erratic, with a decrease during 1997 due to a closure caused by a fire in a freight shuttle. The total freight crossings increased over the period, indicating the substitutability of the tunnel by sea crossings. The tunnel has achieved a cross-Channel freight traffic market share close to or above Eurotunnel's 1980s predictions but Eurotunnel's 1990 and 1994 predictions were overestimates.

For freight transported on through freight trains, the first year freight prediction was 7.2 million gross tonnes, however, the actual 1995 figure was 1.3 million gross tonnes.[59] Through freight volumes peaked in 1998 at 3.1 million tonnes. However, with continuing problems, this figure fell back to 1.21 million tonnes in 2007, increasing again slightly to 1.24 million tonnes in 2008.[61] Together with that carried on freight shuttles, freight traffic growth has occurred since opening, with 6.4 million tonnes carried in 1995, 18.4 million tonnes recorded in 2003[60] and 19.6 million tonnes in 2007.[63] Numbers fell back in the wake of the 2008 fire.

 Year  Freight transported...
by through freight trains[64]
(actual tonnes)
by Eurotunnel Truck Shuttles[60][63]
(estimated, million tonnes)
Total
(estimated, million tonnes)
1994 0 0.8[60] 0.8
1995 1,349,802 5.1 6.4
1996 2,783,774 6.7 9.5
1997 2,925,171 3.3 6.2
1998 3,141,438 9.2 12.3
1999 2,865,251 10.9 13.8
2000 2,947,385 14.7 17.6
2001 2,447,432 15.6 18.0
2002 1,463,580 15.6 17.1
2003 1,743,686[66] 16.7 18.4
2004 1,889,175[67] 16.6 18.5
2005 1,587,790[67] 17.0 18.6
2006 1,569,429[68] 16.9 18.5
2007 1,213,647[68] 18.4 19.6
2008 1,239,445[69] 14.2 15.4
2009 1,181,089[69] 10.0 11.2
2010[65] 1,128,079[62] 14.2 15.3

Eurotunnel's freight subsidiary is Europorte 2.[70] In September 2006 EWS, the UK's largest rail freight operator, announced that owing to cessation of UK-French government subsidies of £52 million per annum to cover the Channel Tunnel "Minimum User Charge" (a subsidy of around £13,000 per train, at a traffic level of 4,000 trains per annum), freight trains would stop running after 30 November.[71]

Economic performance

Shares in Eurotunnel were issued at £3.50 per share on 9 December 1987. By mid-1989 the price had risen to £11.00. Delays and cost overruns led to the share price dropping; during demonstration runs in October 1994 the share price reached an all-time low value. Eurotunnel suspended payment on its debt in September 1995 to avoid bankruptcy.[72] In December 1997 the British and French governments extended Eurotunnel's operating concession by 34 years to 2086. Financial restructuring of Eurotunnel occurred in mid-1998, reducing debt and financial charges. Despite the restructuring The Economist reported in 1998 that to break even Eurotunnel would have to increase fares, traffic and market share for sustainability.[73] A cost benefit analysis of the Channel Tunnel indicated that there were few impacts on the wider economy and few developments associated with the project, and that the British economy would have been better off if the tunnel had not been constructed.[60][74]

Under the terms of the Concession, Eurotunnel was obliged to investigate a cross-Channel road tunnel. In December 1999 road and rail tunnel proposals were presented to the British and French governments, but it was stressed that there was not enough demand for a second tunnel.[75] A three-way treaty between the United Kingdom, France and Belgium governs border controls, with the establishment of control zones wherein the officers of the other nation may exercise limited customs and law enforcement powers. For most purposes these are at either end of the tunnel, with the French border controls on the UK side of the tunnel and vice versa. For certain city-to-city trains, the train itself represents a control zone.[76] A binational emergency plan coordinates UK and French emergency activities.[77]

In 1999 Eurostar posted its first ever net profits, having previously made a loss of £925m in 1995.[25]

Terminals

The terminals sites are at Cheriton (Folkestone in the United Kingdom) and Coquelles (Calais in France). The terminals are unique facilities designed to transfer vehicles from the motorway onto trains at a rate of 700 cars and 113 heavy vehicles per hour. The UK site uses the M20 motorway. The terminals are organised with the frontier controls juxtaposed with the entry to the system to allow travellers to go onto the motorway at the destination country immediately after leaving the shuttle. The area of the UK site was severely constrained and the design was challenging. The French layout was achieved more easily. To achieve design output, the shuttles accept cars on double-decks; for flexibility, ramps were placed inside the shuttles to provide access to the top decks.[78] At Folkestone there are 20 kilometres (12 mi) of mainline track and 45 turnouts with eight platforms. At Calais there are 30 kilometres (19 mi) of track with 44 turnouts. At the terminals the shuttle trains traverse a figure eight to reduce uneven wear on the wheels.[53] There is a freight marshalling yard west of Cheriton at Dollands Moor Freight Yard.

Regional impact

A 1996 report from the European Commission predicted that Kent and Nord-Pas de Calais had to face increased traffic volumes due to general growth of cross-Channel traffic and traffic attracted by the tunnel. In Kent, a high-speed rail line to London would transfer traffic from road to rail.[79] Kent's regional development would benefit from the tunnel, but being so close to London restricts the benefits. Gains are in the traditional industries and are largely dependent on the development of Ashford International passenger station, without which Kent would be totally dependent on London's expansion. Nord-Pas-de-Calais enjoys a strong internal symbolic effect of the Tunnel which results in significant gains in manufacturing.[80]

The removal of a bottleneck by means like the Channel Tunnel does not necessarily induce economic gains in all adjacent regions. The image of a region being connected to the European high-speed transport and active political response are more important for regional economic development. However, some small-medium enterprises located in the immediate vicinity of the terminal have used the opportunity to re-brand the profile of their business with positive effect, such as The New Inn at Etchinghill which was able to commercially exploit its unique selling point as being 'the closest pub to the Channel Tunnel'. Tunnel-induced regional development is small compared to general economic growth.[81] The South East of England is likely to benefit developmentally and socially from faster and cheaper transport to continental Europe, but the benefits are unlikely to be equally distributed throughout the region. The overall environmental impact is almost certainly negative.[82]

Since the opening of the tunnel, small positive impacts on the wider economy have been felt, however, it is difficult to identify major economic successes directly attributed to the tunnel.[83] The Eurotunnel does operate profitably, offering an alternative transportation mode unaffected by poor weather.[84] both Eurotunnel and Eurostar. High costs of construction did delay profitability, however, and companies involved in the Channel Tunnel's construction and operation early in operation relied on government aid to deal with debts amounted.[85][86][87] Eurotunnel has been described as being in a serious situation.[88]

Incidents

Fires

There have been three fires in the Channel Tunnel that were significant enough to close the tunnel—all on the heavy goods vehicle (HGV) shuttles—and other more minor incidents.

During an "invitation only" testing phase on 9 December 1994, a fire broke out in a Ford Escort car whilst its owner had been loading it on to the upper deck of a tourist shuttle. The fire started at approximately 10:00 with the shuttle train stationary in the Folkestone terminal and was extinguished around 40 minutes later with no passenger injuries.[89]

On 18 November 1996, a fire broke out on a heavy goods vehicle shuttle wagon in the tunnel but nobody was seriously hurt. The exact cause is unknown,[90] although it was not a Eurotunnel equipment or rolling stock problem; it may have been due to arson of a heavy goods vehicle. It is estimated that the heart of the fire reached 1,000 °C (1,800 °F), with the tunnel severely damaged over 46 metres (151 ft), with some 500 metres (1,640 ft) affected to some extent. Full operation recommenced six months after the fire.[91]

The tunnel was closed for several hours on 21 August 2006, when a truck on an HGV shuttle train caught fire.[92][93] On 11 September 2008, a fire occurred in the Channel Tunnel at 13:57 GMT. The incident started on a freight-carrying vehicle train travelling towards France.[94] The event occurred 11 kilometres (6.8 mi) from the French entrance to the tunnel. No one was killed but several people were taken to hospitals suffering from smoke inhalation, and minor cuts and bruises. The tunnel was closed to all traffic, with the undamaged South Tunnel reopening for limited services two days later.[95] Full service resumed on 9 February 2009[96] after repairs costing €60 million.

Train failures

On the night of 19/20 February 1996, approximately 1,000 passengers became trapped in the Channel Tunnel when two British Rail Class 373 trains on continent-bound Eurostar service broke down owing to failures of electronic circuits caused by snow and ice being deposited and then melting on the circuit boards.[97]

On 3 August 2007, an electrical failure lasting six hours caused passengers to be trapped in the tunnel on a Eurotunnel shuttle crossing.[98]

On the evening of 18 December 2009, during the December 2009 European snowfall, five London-bound trains operating Eurostar services failed inside the tunnel, trapping 2,000 passengers in the tunnel overnight. Five Class 373 trains had departed from Brussels and Paris and encountered cold temperatures in Northern France, the coldest for eight years.[99] A Eurotunnel spokesperson explained that the problem had arisen because of 'fluffy snow' in France,[100] which had evaded the 'winterisation' shields designed to stop snow getting into the electrics.[101] Electrical failure was then caused by the transition from the cold air in France to the warm atmosphere inside the tunnel.[102] One train from Brussels had been turned back before reaching the tunnel; two trains were hauled out of the tunnel using diesel-powered Eurotunnel Class 0001. The blocking of the Channel Tunnel led to the implementation of Operation Stack, the transformation of the M20 motorway into a linear car park.[103]

Snow that had built up on the trains then melted in the heat of the tunnel, the water causing electrical faults.[104][105][106][107] The occasion was the first time during the fifteen years that a Eurostar train had to be evacuated inside the tunnel itself; the failing of four at once being described as "unprecedented".[108] The Channel Tunnel reopened the following morning.[109] Nirj Deva, Member of the European Parliament for South East England, had called for Eurostar chief executive Richard Brown to resign over the incidents.[110] An independent report by Christopher Garnett (former CEO of Great North Eastern Railway) and Claude Gressier (a French transport expert) on the 18/19 December 2009 incidents was issued in February 2010, making 21 recommendations.[111][112]

A further Class 373 unit on Brussels–London service broke down in the tunnel on 7 January 2010. The train had 236 passengers on board and was towed to Ashford; other trains that had not yet reached the tunnel were turned back.[113][114]

Asylum and immigration

Immigrants and would-be asylum seekers have been known to use the tunnel to attempt to enter Britain. By 1997, the problem had already attracted international press attention, and the French Red Cross opened a refugee centre at Sangatte in 1999, using a warehouse once used for tunnel construction; by 2002 it housed up to 1500 persons at a time, most of them trying to get to the UK.[115] In 2001, most came from Afghanistan, Iraq and Iran, but African and Eastern European countries are also represented.[116]

Most migrants who got into Britain found some way to ride a freight train, but others used Eurostar. Though the facilities were fenced, airtight security was deemed impossible; refugees would even jump from bridges onto moving trains. In several incidents people were injured during the crossing; others tampered with railway equipment, causing delays and requiring repairs.[117] Eurotunnel said it was losing £5m per month because of the problem.[118] A dozen refugees have died in crossing attempts.[115]

In 2001 and 2002, several riots broke out at Sangatte and groups of refugees (up to 550 in a December 2001 incident) stormed the fences and attempted to enter en masse.[119] Immigrants have also arrived as legitimate Eurostar passengers without proper entry papers.[120]

Local authorities in both France and the UK called for the closure of Sangatte, and Eurotunnel twice sought an injunction against the centre.[115] The United Kingdom blamed France for allowing Sangatte to open, and France blamed the UK for its lax asylum rules and the EU for not having a uniform immigration policy.[118] The cause célèbre nature of the problem even included journalists detained as they followed refugees onto railway property.[121]

In 2002, after the European Commission told France that it was in breach of European Union rules on the free transfer of goods, because of the delays and closures as a result of its poor security, a double fence was built at a cost of £5 million, reducing the numbers of refugees detected each week reaching Britain on goods trains from 250 to almost none.[122] Other measures included CCTV cameras and increased police patrols.[123] At the end of 2002, the Sangatte centre was closed after the UK agreed to take some of its refugees.[124]

Safety

The Channel Tunnel Safety Authority is responsible for some aspects of safety regulation in the tunnel; it reports to the IGC.[125]

The service tunnel is used for access to technical equipment in cross-passages and equipment rooms, to provide fresh-air ventilation, and for emergency evacuation. The Service Tunnel Transport System (STTS) allows fast access to all areas of the tunnel. The service vehicles are rubber-tyred with a buried guidance wire system. Twenty-four STTS vehicles were made, and are used mainly for maintenance but also for firefighting and in emergencies. "Pods" with different purposes, up to a payload of 2.5–5 t (2.8–5.5 tons), are inserted into the side of the vehicles. The STTS vehicles cannot turn around within the tunnel, and are driven from either end. The maximum speed is 80 km/h (50 mph) when the steering is locked. A smaller fleet of fifteen Light Service Tunnel Vehicles (LADOGS) were introduced to supplement the STTSs. The LADOGS have a short wheelbase with a 3.4 m (11 ft) turning circle allowing two-point turns within the service tunnel. Steering cannot be locked like the STTS vehicles, and maximum speed is 50 km/h (31 mph). Pods up to 1 tonne can be loaded onto the rear of the vehicles. Drivers in the tunnel sit on the right, and the vehicles drive on the left. Owing to the risk of French personnel driving on their native right side of the road, sensors in the road vehicles alert the driver if the vehicle strays to the right side of the tunnel.[126]

The three tunnels contain 6,000 tonnes (6,600 tons) of air that needs to be conditioned for comfort and safety. Air is supplied from ventilation buildings at Shakespeare Cliff and Sangatte, with each building capable of full duty providing 100% standby capacity. Supplementary ventilation also exists on either side of the tunnel. In the event of a fire, ventilation is used to keep smoke out of the service tunnel and move smoke in one direction in the main tunnel to give passengers clean air. The Channel Tunnel was the first mainline railway tunnel to have special cooling equipment. Heat is generated from traction equipment and drag. The design limit was set at 30 °C (86 °F), using a mechanical cooling system with refrigeration plants on both the English and French sides that run chilled water circulating in pipes within the tunnel.[127]

Trains travelling at high speed create piston-effect pressure changes that can affect passenger comfort, ventilation systems, tunnel doors, fans and the structure of the trains, and drag on the trains.[127] Piston relief ducts of 2-metre (7 ft) diameter were chosen to solve the problem, with 4 ducts per kilometre to give close to optimum results. Unfortunately this design led to unacceptable lateral forces on the trains so a reduction in train speed was required and restrictors were installed in the ducts.[128]

The safety issue of a fire on a passenger-vehicle shuttle garnered much attention, with Eurotunnel itself noting that fire was the risk gathering the most attention in a 1994 Safety Case for three reasons: ferry companies opposed to passengers being allowed to remain with their cars; Home Office statistics indicating that car fires had doubled in ten years; and the long length of the tunnel. Eurotunnel commissioned the UK Fire Research Station to give reports of vehicle fires, as well as liaising with Kent Fire Brigade to gather vehicle fire statistics over one year. Fire tests took place at the French Mines Research Establishment with a mock wagon used to investigate how cars burned.[129] The wagon door systems are designed to withstand fire inside the wagon for 30 minutes, longer than the transit time of 27 minutes. Wagon air conditioning units help to purge dangerous fumes from inside the wagon before travel. Each wagon has a fire detection and extinguishing system, with sensing of ions or ultraviolet radiation, smoke and gases that can trigger halon gas to quench a fire. Since the Heavy Goods Vehicle (HGV) wagons are not covered, fire sensors are located on the loading wagon and in the tunnel itself. A 10-inch (250 mm) water main in the service tunnel provides water to the main tunnels at 125-metre (410 ft) intervals.[130] The ventilation system can control smoke movement. Special arrival sidings exist to accept a train that is on fire, as the train is not allowed to stop whilst on fire in the tunnel. Eurotunnel has banned a wide range of hazardous goods from travelling in the tunnel. Two STTS vehicles with firefighting pods are on duty at all times, with a maximum delay of 10 minutes before they reach a burning train.[91]

See also

Notes

  1. ^ Oxford Dictionary of English (2nd Edition Revised ed.). OUP Oxford. 11 August 2005. ISBN 3411021446. 
  2. ^ Janet Stobart (20 December 2009). "Rail passengers spend a cold, dark night stranded in Chunnel". L.A. Times. http://articles.latimes.com/2009/dec/20/world/la-fg-chunnel20-2009dec20. Retrieved 27 June 2010. 
  3. ^ "The Channel Tunnel". raileurope.com. http://www.raileurope.com/us/rail/eurostar/channel_tunnel.htm. Retrieved 19 July 2009. 
  4. ^ a b Institute of Civil Engineers p. 95
  5. ^ "Turkey Building the World's Deepest Immersed Tube Tunnel". Popular Mechanics. http://www.popularmechanics.com/science/extreme_machines/4217338.html?series=23. Retrieved 19 July 2009. 
  6. ^ a b Chisholm, Michael (1995). Britain on the edge of Europe. London: Routledge. p. 151. ISBN 0415119219. 
  7. ^ a b Reynolds, Christopher (19 May 1996). "Seven Wonders of the World: The Modern List". The Plain Dealer. 
  8. ^ a b Whiteside p. 17
  9. ^ "The Channel Tunnel". library.thinkquest.org. http://library.thinkquest.org/5983/pages/chunnel.htm. Retrieved 19 July 2009. 
  10. ^ a b c d e f g h i j Wilson pp. 14–21
  11. ^ a b Flyvbjerg et al. p. 12
  12. ^ "Four men caught in Channel Tunnel". BBC News. 4 January 2008. http://news.bbc.co.uk/1/hi/england/kent/7171985.stm. Retrieved 19 July 2009. 
  13. ^ "Sangatte refugee camp". The Guardian (UK). http://www.guardian.co.uk/uk/2002/may/23/immigration.immigrationandpublicservices1. Retrieved 19 July 2009}. 
  14. ^ "Subterranea Britannica: Channel Tunnel – 1880 attempt". subbrit.org. http://www.subbrit.org.uk/sb-sites/sites/c/channel_tunnel_1880_attempt/index.shtml. Retrieved 19 July 2009. 
  15. ^ Whiteside pp. 18–23
  16. ^ "The Proposed Tunnel Between England and France" (PDF). The New York Times. 7 August 1866. http://query.nytimes.com/mem/archive-free/pdf?res=9A00EFD9133DE53BBC4F53DFBE66838D679FDE. Retrieved 3 January 2008. 
  17. ^ Gladstone, William (1902). A. W. Hutton & H.J. Cohen. ed. The Speeches Of The Right Hon. W. E. Gladstone On Home Rule, Criminal Law, Welsh And Irish Nationality, National Debt And The Queen's Reign. The Speeches And Public Addresses Of The Right Hon. W. E. Gladstone, M.P.. X. London: Methuen And Company. 
  18. ^ MacMillan, Margaret. "Paris 1919". Random House, 2002, p. 174, 194
  19. ^ "New Plan for Channel Tunnel" Popular Mechanics, May 1929, pp. 767-768
  20. ^ "Channel Tunnel Site Investigation - 1964 - Halcrow Group". Halcrow Group. 13 July 2011. http://www.halcrow.com/Who-we-are/film_archive/Channel-Tunnel-site-investigation-film/. Retrieved 26 July 2011.  Online presentation of a 1964–65 film documentary of a geological survey of the Channel, with a brief summary.
  21. ^ Kirkland pp. 10–11
  22. ^ "Parliamentary note on the Channel Tunnel Rail Link". House of Commons Library. http://www.parliament.uk/commons/lib/research/briefings/snbt-00070.pdf. Retrieved 5 April 2010. 
  23. ^ a b c Flyvbjerg et al. pp. 96–97
  24. ^ Flyvbjerg et al. p. 3
  25. ^ a b "On this day: Tunnel links UK and Europe". BBC News. 1 December 1990. http://news.bbc.co.uk/onthisday/hi/dates/stories/december/1/newsid_2516000/2516473.stm. Retrieved 19 July 2009. 
  26. ^ a b c Anderson, pp. xvi–xvii
  27. ^ Harlow, John (2 April 1995). "Phantom Trains Wreak Havoc in Channel Tunnel". The Times (UK). 
  28. ^ "ingenious: Navvies". ingenious. 11 March 2008. http://www.ingenious.org.uk/Read/Identity/RailwaysandIdentity/Navvies/. Retrieved 19 July 2009. 
  29. ^ "Thirteen workers die as safety standards are ignored in race to build Olympic sites". The Independent (UK). 3 April 2004. http://www.independent.co.uk/news/world/europe/thirteen-workers-die-as-safety-standards-are-ignored-in-race-to-build-olympic-sites-558698.html. Retrieved 26 September 2008. 
  30. ^ Glenn Frankel (31 October 1990). "Britain and France Link Up-at Last". The Washington Post. 
  31. ^ "Chunnel birthday". Evening Mail (Birmingham Post & Mail Ltd). 2 December 2000. 
  32. ^ a b "On This Day – 1994: President and Queen open Chunnel". BBC News. 6 May 1994. http://news.bbc.co.uk/onthisday/hi/dates/stories/may/6/newsid_2511000/2511653.stm. Retrieved 12 January 2008. 
  33. ^ Woodman, Peter (14 November 2007). "High-speed Rail Link Finally Completed". Press Association National Newswire. 
  34. ^ "New high-speed rail line opens to link Britain to Europe". Channel NewsAsia (MediaCorp News). 15 November 2007. 
  35. ^ Gilbert, Jane (1 December 2006). "`Chunnel' workers link France and Britain". The Daily Post (New Zealand) (APN New Zealand Ltd). 
  36. ^ Kirkland p. 13
  37. ^ Institute of Civil Engineers p. 208
  38. ^ Flyvbjerg et al. p. 51
  39. ^ Harris, C.S. et al., ed (1996). Engineering Geology of the Channel Tunnel. London: Thomas Telford. p. 57. ISBN 0727720457. 
  40. ^ a b c Kirkland pp. 21–50
  41. ^ a b c Kirkland pp. 22–26
  42. ^ a b c d Kirkland pp. 63–128
  43. ^ Wilson p. 38
  44. ^ Kirkland p. 29
  45. ^ Wilson p. 44
  46. ^ Kirkland pp. 117–128
  47. ^ Pierre-Jean Pompee. "Channel Tunnel: Tunnel's Construction". pagesperso-orange.fr. http://pagesperso-orange.fr/batisseurs-tunnel/3tunnels.pdf. Retrieved 19 July 2009. 
  48. ^ Kirkland pp. 129–132
  49. ^ Kirkland pp. 134–148
  50. ^ a b Article: Railway electric traction 9 August 2009
  51. ^ Kirkland pp. 149–155
  52. ^ Article-de: Eurotunnel#Betrieb 9 August 2009
  53. ^ a b Kirkland pp. 157–174
  54. ^ "Strategic Freight Network: The Longer-Term Vision". Department for Transport. http://www.dft.gov.uk/pgr/rail/strategyfinance/strategy/freightnetwork/. Retrieved 17 May 2009. 
  55. ^ Kirkland pp. 175–211
  56. ^ Edmonds, Sam (16 December 2009). "Deutsche Bahn gets access to Channel Tunnel". Deutsche Welle. http://www.dw-world.de/dw/article/0,,5018915,00.html?maca=en-rss-en-all-1573-rdf. Retrieved 20 December 2009. 
  57. ^ "Deutsche Bahn allowed through chunnel". Austin News. 16 December 2009. http://www.austinnews.net/story/578370. Retrieved 20 December 2009. 
  58. ^ http://www.bahn.com/i/view/GBR/en/about/overview/ice-in-london.shtml
  59. ^ a b Flyvbjerg et al. p. 22
  60. ^ a b c d e f g Ricard Anguera (May 2006). "The Channel Tunnel—an ex post economic evaluation". Transportation Research Part A: Policy and Practice 40 (4): 291–315. doi:10.1016/j.tra.2005.08.009. 
  61. ^ a b "Eurotunnel 2008 traffic and revenue figures". Eurotunnel. 15 January 2009. http://www.eurotunnel.com. Retrieved 15 January 2009. 
  62. ^ a b "Eurotunnel 2010 traffic and revenue figures". Eurotunnel. 18 January 2011. http://www.eurotunnelgroup.com/uploadedFiles/assets-uk/Media/Press-Releases/2011-Press-Releases/110118Eurotunnel-traffic-and-revenue.pdf. Retrieved 6 February 2011. 
  63. ^ a b c d "Traffic figures". Eurotunnel. http://www.eurotunnel.com/ukcP3Main/ukcCorporate/ukcTheGroup/ukcOperations/ukpTraffic. Retrieved 15 January 2009. 
  64. ^ a b "Study Report Annex 2". Initial East Kent and Ashford Sub-Regional Study for The South East Plan. South East England Regional Assembly. June 2004. pp. Table 11. http://www.southeast-ra.gov.uk/southeastplan/key/study_areas/initial_studies/east_kent_ashford_annex%202.xls. Retrieved 21 January 2009. 
  65. ^ a b "Traffic figures". Eurotunnel. http://www.eurotunnelgroup.com/uk/eurotunnel-group/operations/traffic-figures/. Retrieved 6 February 2011. 
  66. ^ "Eurotunnel 2003 Revenue & Traffic". Eurotunnel. 20 January 2004. http://www.eurotunnel.com/ukcP3Main/ukcCorporate/ukcMediaCentre/ukcNewsReleases/ukcNews2004/ukcJanuary2004/ukpPr0401Revenue.htm. Retrieved 21 January 2009. 
  67. ^ a b "Eurotunnel: 2005 Traffic and revenue figures.". Eurotunnel. 16 January 2006. http://www.eurotunnel.com/ukcP3Main/ukcCorporate/ukcMediaCentre/ukcNewsReleases/ukcNews2006/ukcJanuary2006/ukpPr06012005TrafficAndRevenue.htm. Retrieved 21 January 2009. 
  68. ^ a b "Eurotunnel 2007 Traffic and Revenue figures: a remarkable year". Eurotunnel. 15 January 2008. http://www.eurotunnel.com/ukcP3Main/ukcCorporate/ukcMediaCentre/ukcNewsReleases/ukcNews2008/ukcJanuary2008/ukpPr0801TrafficAndRevenue2007.htm. Retrieved 21 January 2009. 
  69. ^ a b "Eurotunnel 2009 traffic and revenue figures". Eurotunnel. 10 January 2010. http://www.eurotunnelgroup.com/assets-uk/media/press-releases/2010-press-releases/100120TrafficRevenueFiguresyear2009/. Retrieved 6 February 2011. 
  70. ^ "Eurotunnel gets backing for freight service". AFX (Agence France Presse). 28 October 2004. 
  71. ^ Dominic O'Connell (3 September 2006). "Chunnel cash row threatens freight trains". The Times (UK). http://business.timesonline.co.uk/tol/business/industry_sectors/transport/article626416.ece. Retrieved 3 September 2006. 
  72. ^ "Megaprojects and Risk: An Anatomy of Ambition". josephcoates.com. http://www.josephcoates.com/pdf_files/268_Megaprojects_and_Risk.pdf. Retrieved 19 July 2009. 
  73. ^ Flyvbjerg et al. pp. 32–34
  74. ^ Flyvbjerg, B. Buzelius, N. Rothengatter, W (2003). Megaprojects and Risk. Cambridge: Cambridge University Press. pp. 68–69. ISBN 0521009464. 
  75. ^ "The CPS: Channel Tunnel". Crown Prosecution Service. http://www.cps.gov.uk/legal/section2/chapter_f.html#_Toc44570638. Retrieved 11 March 2008. 
  76. ^ Kirkland p. 331
  77. ^ Kirkland pp. 255–270
  78. ^ European Commission pp. 220–222
  79. ^ European Commission pp. 248–252
  80. ^ Fayman, Sonia; Metge, Pierre (September 1995). "The regional impact of the Channel Tunnel: Qualitative and quantitative analysis". European Planning Studies 3 (3): 333. 
  81. ^ Button, Kenneth (July 1990). "The Channel Tunnel: The Economic Implications for the South East of England". The Geographical Journal (Blackwell Publishing) 156 (2): 187–199. doi:10.2307/635327. JSTOR 635327. 
  82. ^ Flyvbjerg et al. p. 68–69
  83. ^ "Eurotunnel revenues boosted by shuttle demand". BBC (UK). 18 January 2011. http://www.bbc.co.uk/news/business-12213425. Retrieved 18 January 2011. 
  84. ^ Harrison, Michael (10 February 2004). "Eurotunnel calls for government support after record £1.3bn loss". The Independent (UK). http://www.independent.co.uk/news/business/news/eurotunnel-calls-for-government-support-after-record-acircpound13bn-loss-569459.html. Retrieved 21 July 2009. 
  85. ^ "Eurotunnel has £4bn too much debt". The Telegraph (London). 12 January 2005. http://www.telegraph.co.uk/finance/2917255/Eurotunnel-has-4bn-too-much-debt.html. Retrieved 21 July 2009. 
  86. ^ Clark, Andrew (21 February 2006). "Debt-laden Channel tunnel rail link is 'nationalised'". The Guardian (UK). http://www.guardian.co.uk/business/2006/feb/21/transportintheuk.politics. Retrieved 21 July 2009. 
  87. ^ "Facts and figures Eurotunnel 2000-2004/Forecast 2005: Commentry and a suggestion". Adacte.com. June 2005. http://www.adacte.com/economiepolitique/hollandais17062005.doc. Retrieved 21 July 2009. 
  88. ^ Wolmar, Christian (10 December 1994). "Fire raises Channel Tunnel fears". The Independent (London). http://www.independent.co.uk/news/fire-raises-channel-tunnel-fears-1389084.html. Retrieved 25 December 2009. 
  89. ^ "Inquiry into the fire on Heavy Goods Vehicle Shuttle 7539 on 18 November 1996". Channel Tunnel Safety Authority. May 1997. ISBN 0115519319. http://www.railwaysarchive.co.uk/documents/CTSA_ChanTun1996.pdf. Retrieved 21 July 2009. 
  90. ^ a b C. J. Kirkland (2002). "The fire in the Channel Tunnel" (PDF). Tunnelling and Underground Space Technology 17: 129–132. doi:10.1016/S0886-7798(02)00014-7. http://www.ita-aites.org/cms/fileadmin/filemounts/ovion/doc/safety/sydney/OS12.PDF. 
  91. ^ "Lorry fire closes Channel Tunnel". BBC News. 21 August 2006. http://news.bbc.co.uk/2/hi/uk_news/england/5271784.stm. Retrieved 21 August 2006. 
  92. ^ Rail Accident Investigation Branch (October 2007). Fire on HGV shuttle in the Channel Tunnel 21 August 2006 (Report). Rail Accident Report. Department for Transport. http://www.raib.gov.uk/cms_resources/071023_R372007_Channel%20Tunnel.pdf. 
  93. ^ Robert Wright (12 September 2008). "Channel tunnel fire causes further cancellations". Financial Times. http://www.ft.com/cms/s/0/ad05c7e6-8062-11dd-99a9-000077b07658.html. Retrieved 21 July 2009. 
  94. ^ "Channel Tunnel Fire Evacuation". Sky News. 11 September 2008. http://news.sky.com/skynews/Home/UK-News/Channel-Tunnel-Closed-Due-To-A-Fire/Article/200809215097705?lpos=UK%2BNews_0&lid=ARTICLE_15097705_Channel%2BTunnel%2BClosed%2BDue%2BTo%2BA%2BFire. Retrieved 9 March 2009. 
  95. ^ "Eurotunnel fully open to traffic". Eurotunnel.com. http://www.eurotunnel.com/ukcP3Main/ukcCorporate/ukcMediaCentre/ukcNewsReleases/ukcNews2009/ukcFebruary2009/ukpPr0902Eurotunnel-back-to-full-capacity.htm. Retrieved 14 January 2010. 
  96. ^ Wolmar, Christian (22 February 1996). "Wrong kind of snow in tunnel...". The Independent (UK). http://www.independent.co.uk/news/wrong-kind-of-snow-in-tunnel-1320248.html. Retrieved 21 December 2009. 
  97. ^ "Delays after Channel Tunnel fault". BBC News. 3 August 2007. http://news.bbc.co.uk/1/hi/england/kent/6929713.stm. Retrieved 14 January 2010. 
  98. ^ "Severe Weather Brings Eurostar To A Halt". Sky News. 19 December 2009. http://news.sky.com/skynews/Home/UK-News/Eurostar-Says-All-Scheduled-Services-Tomorrow-Have-Been-Cancelled/Article/200912315504284. Retrieved 19 December 2009. 
  99. ^ Eurostar blames 'fluffy' snow for weekend chaos The Times 21 December 09
  100. ^ Eurostar cancels trains over snowPress Association (21 December 09)
  101. ^ Cole, Rob (18 December 2009). "'Nightmare' Over For Stranded Passengers". Sky News. http://news.sky.com/skynews/Home/UK-News/Eurostar-Trains-Trapped-In-Channel-Tunnel-As-Snow-And-Ice-Brings-Services-To-A-Halt/Article/200912315504284. Retrieved 19 December 2009. 
  102. ^ "Passengers home after trapped in Channel Tunnel". The Press Association. 19 December 2009. http://www.google.com/hostednews/ukpress/article/ALeqM5hRM5rF7ThMd2awfWzOXBFJ7AmuXg. Retrieved 19 December 2009. 
  103. ^ Gray, Melissa (19 December 2009). "Eurostar services cancelled as snow brings havoc". CNN. http://www.cnn.com/2009/WORLD/europe/12/19/channel.tunnel/. Retrieved 19 December 2009. 
  104. ^ Mansey, Kate; Owens, Nick; Jones, Crystal (20 December 2009). "Eurostar passengers told not to breathe so hard as they ran out of air". Daily Mirror. http://www.mirror.co.uk/news/top-stories/2009/12/20/eurostar-passengers-told-not-to-breathe-so-hard-as-they-ran-out-of-air-115875-21909898/. Retrieved 19 December 2009. 
  105. ^ Randall, David; Lakhani, Nina (20 December 2009). "Thousands stranded in Eurostar chaos". Independent (London). http://www.independent.co.uk/news/uk/home-news/thousands-stranded-in-eurostar-chaos-1845914.html. Retrieved 20 December 2009. 
  106. ^ "Passengers trapped on Eurostar trains relive ordeal". BBC News. 20 December 2009. http://news.bbc.co.uk/1/hi/uk/8422305.stm. Retrieved 20 December 2009. 
  107. ^ "Chaos in Eurotunnel as several trains break down". Amsterdam News.Net. 19 December 2009. http://www.amsterdamnews.net/story/579422. Retrieved 19 December 2009. ""Four Eurostars broken down at one time — it's absolutely unprecedented", John Keefe of Eurotunnel ... "There's never actually been an evacuation of a Eurostar train in the fifteen years that the tunnel has been opened and last night we evacuated two whole trains to get people off"," 
  108. ^ "Eurotunnel rescues Eurostar". Eurotunnel Press Release. 19 December 2009. http://www.eurotunnel.com/NR/rdonlyres/E69E8275-E4E9-4B65-AC6A-D5A8E9931DD7/0/091219Eurotunnel_rescues_Eurostar.pdf. Retrieved 23 December 2009. 
  109. ^ "Eurostar transports 500 vulnerable passengers to France". BBC News. 20 December 2009. http://news.bbc.co.uk/1/hi/uk/8422978.stm. Retrieved 14 January 2010. 
  110. ^ Woodman, Peter (12 February 2010). "Eurostar rapped over Channel Tunnel breakdown – News & Advice, Travel". The Independent (UK). http://www.independent.co.uk/travel/news-and-advice/eurostar-rapped-in-tunnel-breakdowns-report-1897410.html. Retrieved 27 April 2010. 
  111. ^ Garnett, Christopher; Gressier, M. Claude (12 February 2010). "Eurostar Independent Review" (PDF report). Eurostar. http://www.eurostarindependentreview.org/pdf/Eurostar%20Independent%20Review.pdf. Retrieved 27 April 2010. 
  112. ^ "Eurostar disrupted after new breakdown in Channel tunnel". The Independent (London). 7 January 2009. http://www.independent.co.uk/travel/news-and-advice/eurostar-disrupted-after-new-breakdown-in-channel-tunnel-1861132.html. Retrieved 7 January 2009. 
  113. ^ "Stricken Eurostar train towed out of Channel Tunnel". Uk.reuters.com. 7 January 2010. http://uk.reuters.com/article/idUKTRE6061L020100107. Retrieved 14 January 2010. 
  114. ^ a b c Pierre Kremer (February 2002). "Sangatte: A place of hope and despair". The Magazine of the International Red Cross and Red Crescent Movement. http://www.redcross.int/EN/mag/magazine2002_2/sangatte.html. Retrieved 4 August 2006. 
  115. ^ Caryl Phillips (17 November 2001). "Strangers in a strange land". The Guardian (UK). http://www.guardian.co.uk/saturday_review/story/0,3605,595996,00.html. Retrieved 4 August 2006. 
  116. ^ Avril Stephens (31 July 2007). "Desperate journeys fraught with danger". CNN. http://archives.cnn.com/2001/WORLD/europe/07/31/immigration.daring/index.html. Retrieved 4 August 2006. 
  117. ^ a b "Europe's most notorious refugee camp". BBC News. 12 July 2002. http://212.58.226.40/1/hi/uk/2003977.stm. Retrieved 5 August 2006. 
  118. ^ Paul Webster (27 December 2007). "Police braced for new tunnel raid". The Guardian (UK). http://www.guardian.co.uk/world/2001/dec/27/immigration.uk. Retrieved 4 August 2006. 
  119. ^ "UK/Ireland: Asylum (news digest)". Migration News. 1998 (?). http://migration.ucdavis.edu/MN/more.php?id=1529_0_4_0. Retrieved 4 August 2006. 
  120. ^ "2001 World Press Freedom Review: France". International Press Institute. Archived from the original on 24 October 2007. http://web.archive.org/web/20071024205028/http://www.freemedia.at/cms/ipi/freedom_detail.html?country=/KW0001/KW0003/KW0060/&year=2001. Retrieved 4 August 2006. 
  121. ^ "Sangatte asylum talks due". BBC News. 26 September 2002. http://news.bbc.co.uk/2/hi/europe/2282306.stm. Retrieved 4 August 2006. 
  122. ^ "Tunnel security to be tightened". BBC News. 31 May 2002. http://news.bbc.co.uk/1/hi/uk_politics/2017789.stm. Retrieved 4 August 2006. 
  123. ^ Philip Delves Broughton and Andrew Sparrow (27 September 2002). "Blunkett reaches deal to shut Sangatte camp". Daily Telegraph (UK). http://www.telegraph.co.uk/news/worldnews/europe/france/1408494/Blunkett-reaches-deal-to-shut-Sangatte-camp.html. Retrieved 25 February 2009. 
  124. ^ [1233-01-01 "Channel Tunnel : Safety bodies : About the rail industry : Office of Rail Regulation"]. 30 October 2010. 1233-01-01. Retrieved 30 October 2010. 
  125. ^ Kirkland pp. 247–254
  126. ^ a b Kirkland pp. 212–230
  127. ^ The Channel Tunnel Experience Lessons for the Future pp. 19–23
  128. ^ Kirkland pp. 231–240
  129. ^ McFarlane, Andrew (12 September 2008). "Focus turns to cause of tunnel blaze". BBC News. http://news.bbc.co.uk/1/hi/uk/7612776.stm. Retrieved 12 September 2008 21. 

References

  • Anderson, Graham; Roskrow, Ben (1994). The Channel Tunnel Story. London: E & F N Spon. ISBN 041919620X. 
  • European Commission. Directorate-General for Regional Policy and Cohesion. (1996). The regional impact of the Channel Tunnel throughout the Community. Luxembourg: European Commission. ISBN 9282688046. 
  • Flyvbjerg, B. Buzelius, N. Rothengatter, W. (2003). Megaprojects and Risk. Cambridge: Cambridge University Press. ISBN 0521009464. 
  • Institution of Civil Engineers (1989). The Channel Tunnel. London: Thomas Telford. ISBN 0727715461. 
  • Kirkland, Colin J., ed. (1995). Engineering the Channel Tunnel. London: Chapman and Hall. ISBN 0419179208. 
  • Whiteside, Thomas (1962). The Tunnel under the Channel. Rupert Hart-Davis. ISBN 0684832437. 
  • Wilson, Jeremy; Spick, Jerome (1994). Eurotunnel — The Illustrated Journey. HarperCollins. ISBN 0002555395. 

External links